How to Plan and Deliver a Basic Full Bar Renovation in Madrid

Reference date: 28 August 2026.

Buying commercial premises in Madrid and converting them into a bar is not simply a property transaction. The success of the investment depends on whether the intended activity is legally and technically feasible, whether the refurbishment budget reflects the actual condition of the premises, and whether the business has enough working capital to cover the opening period.

This guide explains how to assess, plan and deliver a basic full renovation of a 60–150 m² bar in Madrid. It is intended primarily for international investors and English-speaking buyers who may be unfamiliar with Spanish planning procedures, homeowners’ associations, technical regulations and business licensing terminology.

It includes indicative costs, typical timescales, administrative procedures, technical requirements, risk controls and practical templates for assessing the investment before committing to the purchase.

Pricing assumption: unless stated otherwise, all prices exclude VAT. A prudent assumption of 21% Spanish VAT has been applied to construction work, professional services, equipment and supplies for commercial premises. Public administrative fees are not subject to VAT. Whether input VAT can be reclaimed depends on the investor’s tax position and should be confirmed by a Spanish tax adviser.

Important: this guide does not replace a site-specific feasibility report, architectural or engineering design, legal advice or the certificates required from authorised contractors. Madrid planning rules, heritage protection, acoustic protection zones and the rules of the building’s homeowners’ association may restrict or prevent certain solutions.

1. Executive summary

Is buying and renovating a bar in Madrid generally viable?

Reasoning: finishes, furniture and internal layouts can normally be changed. Planning compatibility, means of escape, accessibility, acoustic separation and a legal commercial kitchen extract route may be far harder—or impossible—to resolve after the purchase.

Recommendation: do not complete the purchase until a competent architect or engineer has assessed the proposed activity and the legal, planning, community and technical information has been reviewed. Any letter of intent, deposit or purchase contract should contain conditions allowing the investor to withdraw if the premises prove unsuitable.

Premises Indicative investment excluding VAT Indicative investment including 21% VAT Typical overall programme
60 m² €105,000–€155,000 €127,050–€187,550 4–7 months
100 m² €155,000–€235,000 €187,550–€284,350 5–8 months
150 m² €220,000–€335,000 €266,200–€405,350 6–10 months

These ranges assume a basic full commercial renovation comprising strip-out work, masonry and partitions, renewed building services, standard finishes, bar counter, functional kitchen, toilets, basic acoustic upgrading, minimum fire protection measures, essential furniture and equipment, professional fees and a contingency allowance.

They exclude the purchase price, financing, business transfer payments, franchise fees, premium equipment, structural strengthening, an unapproved pavement café or terrace, and unusually complex kitchen extract work.

The five main investment constraints

  • Planning and activity compatibility: the exact business activity must be permitted at that address.
  • Commercial kitchen extract: the route, legality and condition of the flue can determine whether hot food preparation is possible.
  • Homeowners’ association: extract ducts, rooftop equipment, façades and courtyards may involve shared parts of the building.
  • Acoustics: opening hours, amplified music, equipment and neighbouring homes determine the required level of sound insulation.
  • Technical capacity: electrical power, ventilation, air conditioning, drainage, gas, fire safety, accessibility and escape routes can materially affect the design and budget.

2. Phase 0: due diligence before purchasing

2.1 Document checklist

  • ☐ Obtain a recent Spanish Land Registry extract, known as a nota simple.
  • ☐ Confirm ownership, registered floor area, charges and occupancy status.
  • ☐ Compare the Land Registry, Cadastre, approved plans and physical premises.
  • ☐ Obtain confirmation that there are no outstanding homeowners’ association fees.
  • ☐ Review property tax receipts and any outstanding liabilities affecting the premises.
  • ☐ Request a planning compatibility or feasibility assessment for the intended activity.
  • ☐ Check heritage protection, special planning areas and acoustic protection zones.
  • ☐ Obtain the building’s title deed and homeowners’ association rules.
  • ☐ Review the most recent three to five sets of community meeting minutes.
  • ☐ Confirm whether the community has authorised the extract duct and rooftop equipment.
  • ☐ Review the building inspection report, known as the ITE or IEE.
  • ☐ Identify approved special assessments and upcoming building works.
  • ☐ Obtain previous licences, responsible declarations, drawings and technical projects.
  • ☐ Check whether an existing licence or responsible declaration can be transferred.
  • ☐ Investigate enforcement proceedings, noise complaints, closure orders and sanctions.
  • ☐ Confirm that electricity, water and gas accounts are free from debt.
  • ☐ Prepare an inventory of equipment included in the transaction.
  • ☐ Confirm whether each item is owned, leased or subject to finance.
  • ☐ Review fire protection, air-conditioning, gas and extraction maintenance records.
  • ☐ Obtain food safety and HACCP documentation if an operating business is being acquired.

2.2 Technical inspection

System What to inspect Minimum evidence Warning sign
Electrical installation Available power, distribution board, circuits, earthing and public-assembly requirements Electrical installation certificate, design or technical memorandum Old installation without documentation or insufficient available power
Heating, cooling and ventilation Capacity, outdoor air, condensate drainage and maintenance RITE certificates and registration Air-conditioning without proper ventilation or equipment installed on shared parts without approval
Gas Supply, valves, ventilation, detection and soundness Installation certificate and test records Disconnected or undocumented installation
Fire safety Escape routes, extinguishers, emergency lighting, signage and fire resistance Technical project and certificates Insufficient exit capacity for the intended occupancy
Kitchen extraction Canopy, duct, cross-section, access panels, fan and discharge point Approved drawings, inspection and roof photographs Discharge into a façade or courtyard without confirmed legal acceptance
Acoustics Walls, floors, ceilings, service penetrations, equipment and adjoining homes Acoustic study and baseline measurements Residential neighbours combined with late-night amplified music
Plumbing and drainage Water pressure, hot water, pipework, gradients, traps, manholes and leaks Pressure tests and drainage survey where appropriate Insufficient falls or deteriorated drainage
Building defects Damp, leaks, structure, asbestos-containing materials and pests Technical report and selective opening-up work Active cracking, persistent water ingress or unpriced hazardous materials

Important: electrostatic filters, activated-carbon systems and recirculating hoods are not automatically equivalent to a compliant commercial kitchen flue. They may reduce particles or odours, but they do not remove planning, environmental, ventilation, fire safety, food hygiene or community requirements.

2.3 Legal, tax and corporate matters

  • Choose between operating as a self-employed individual or through a Spanish limited company.
  • Complete the Spanish tax registration and select the correct Economic Activities Tax classification.
  • Prepare a tax calendar covering VAT, payroll, withholding taxes and corporate or personal income tax.
  • Have the purchase, lease or business transfer agreement reviewed by a Spanish lawyer.
  • Arrange public liability, property damage and business interruption insurance.
  • Set up occupational risk prevention and contractor coordination procedures.
  • Review data protection requirements for bookings, Wi-Fi, CCTV, marketing and customer databases.

2.4 Letter of intent template

LETTER OF INTENT — PREMISES AT [ADDRESS]

Buyer: [ ]
Seller: [ ]
Proposed price: €[ ]
Offer valid until: [date]
Negotiation exclusivity: [30–60] days

The proposed acquisition is subject to the buyer being satisfied with:

1. Ownership, charges, debts, registered area and occupation status.
2. A favourable technical report for the intended activity.
3. Planning compatibility and the absence of prohibitive restrictions.
4. Feasibility of escape, accessibility, fire safety and ventilation.
5. A legal and technically viable commercial kitchen extract route.
6. The building rules, meeting minutes and required community approvals.
7. The absence of undeclared sanctions, closure orders or enforcement cases.
8. Approval of finance, where applicable.

If any condition is not satisfied by [date], the buyer may withdraw and
recover all sums paid without penalty.

The seller will provide access, available documentation, permission for
agreed inspections and contact details for the homeowners’ association.

Except for confidentiality, exclusivity, access and deposit-return
provisions, this letter is not intended to create a binding obligation
to complete the purchase.

The final contract should also address representations made by the seller, equipment ownership, debts, community assessments, undisclosed enforcement matters, access for surveys, deposit protection and the precise licences or rights being transferred.

3. Defining the business concept and functional brief

Reasoning: the everyday English word “bar” does not identify the precise Spanish administrative category. Food preparation, amplified music, opening hours, capacity and outdoor seating can substantially change the technical and licensing requirements.

Concept Kitchen requirement Music Technical risk Investor comment
Café Light or moderate Limited background music Medium A balanced option where extraction is viable
Tapas bar Moderate or intensive Background music High Extraction and available electrical power are critical
Cocktail bar Limited Potentially significant High Acoustics, operating hours and neighbours dominate the risk
Gastrobar Intensive Background music Very high Higher capital expenditure and food safety complexity
Bar with amplified music Variable Amplified Very high Do not assume feasibility without activity classification and acoustic design

3.1 Indicative area schedule

Zone 60 m² premises 100 m² premises 150 m² premises
Customer area and circulation 25 m² 45 m² 72 m²
Bar counter and back bar 8 m² 12 m² 16 m²
Kitchen and preparation 10 m² 17 m² 25 m²
Toilets 6 m² 9 m² 12 m²
Storage, cold rooms and waste 6 m² 10 m² 15 m²
Staff, cleaning and plant 5 m² 7 m² 10 m²

These figures are concept-design allowances rather than statutory minimums. Permitted occupancy must be calculated from the actual layout, use, exits, escape distances and clear widths.

3.2 Conceptual layouts

60 m²

[STREET / ENTRANCE]
[CUSTOMER AREA] [BAR]
[ACCESSIBLE WC] [KITCHEN] [STORE / PLANT]


100 m²

[STREET / ENTRANCE]
[MAIN CUSTOMER AREA] [BAR AND COLLECTION]
[TOILETS] [CLEAN/DIRTY KITCHEN] [STORE AND COLD ROOMS]


150 m²

[STREET / ENTRANCE]
[AREA 1] [AREA 2] [LONG BAR]
[TOILETS] [KITCHEN] [WASH-UP] [STORE] [STAFF] [PLANT]

4. Key regulatory requirements in Madrid

4.1 Main authorities and procedures

Area Authority Main documents or procedure Professional Typical timing
Planning, building work and activity Madrid City Council or an authorised ECU Technical project, responsible declaration or licence, municipal fees and construction tax Competent architect or engineer From immediate legal effect for a complete qualifying declaration to 2–6 months or longer for a licence
Opening and operation Madrid City Council Completion certificate and operational documentation where required Design team or works supervisor Approximately 2–8 weeks, depending on the case
Electrical installation Community of Madrid industry authority Design or technical memorandum, installation certificate and registration Authorised installer and engineer where required Approximately 1–4 weeks
Air conditioning and ventilation Community of Madrid industry authority RITE design or memorandum, certificates and registration Authorised RITE contractor Approximately 1–4 weeks
Gas Industry authority and distributor Design where applicable, tests and installation certificate Authorised gas installer Approximately 2–6 weeks
Fire protection City Council and industry authority, depending on the installation CTE DB-SI design justification, equipment certificates and maintenance Competent designer and authorised fire contractor Integrated into the main project
Acoustics Madrid City Council Acoustic study, completion testing and sound limiter where required Acoustic consultant or competent testing body Approximately 1–3 weeks, plus corrective work
Outdoor terrace Madrid City Council or district authority Application, drawings, furniture details, insurance and fees Technical professional where required Approximately 1–4 months or longer

A provisional allowance of approximately €1,500–€6,000 may be made for municipal planning fees and the Spanish construction tax known as ICIO. A broader allowance of €3,000–€10,000 may be required for administration, registrations and fees across the project.

These are budgeting allowances, not official quotations. Actual amounts depend on the type of procedure, floor area, declared construction value, district and current municipal tax ordinances.

4.2 Responsible declaration or licence

A Spanish declaración responsable, or responsible declaration, is a formal statement by the applicant confirming that the proposed work and activity comply with the applicable requirements and that the necessary supporting documentation is available.

Where the procedure is legally available and the submission is complete, it can permit work or operation from the time it enters the municipal register. The City Council retains the power to inspect the premises, request corrections and take enforcement action.

Some interventions require a planning licence instead. The correct route depends on the proposed work, activity, building and planning constraints.

Important: registering a responsible declaration does not prove that the premises comply. The applicant remains responsible for the accuracy of the submission and the physical compliance of the completed work.

4.3 Fire safety

  • Demonstrate compliance with the applicable sections of the Spanish Building Code, particularly CTE DB-SI.
  • Calculate the permitted occupancy.
  • Check escape distances, exit numbers, clear widths and door opening direction.
  • Install suitable fire extinguishers.
  • Provide emergency lighting and photoluminescent signs.
  • Specify compliant surface finishes and fire resistance.
  • Protect special-risk rooms and kitchen areas where required.
  • Certify and maintain fire protection equipment under the RIPCI regulations.

4.4 Accessibility

  • Provide an accessible route from the entrance where required.
  • Resolve thresholds, steps, ramps, doors and approach spaces.
  • Include an accessible toilet where applicable.
  • Provide the necessary turning and transfer spaces.
  • Position grab rails, basins, controls and accessories correctly.
  • Apply CTE DB-SUA and the applicable Community of Madrid accessibility legislation.

The final dimensions must be established by the project designer. The exact requirements may depend on the extent of the work, the existing building and any properly justified technical constraints.

4.5 Commercial kitchen extraction and outdoor air

A kitchen using fryers, griddles, ovens or other equipment producing significant heat, grease, vapour or smoke will usually require capture at source, grease filtration, an independent duct, inspection access, suitable fire protection, a fan, replacement air and an acceptable discharge point.

Option When it may be considered Main limitation
Existing legal roof-level duct Where its route, dimensions and authorisation are documented It may still be damaged, undersized or improperly shared
New duct to roof level Where the route and homeowners’ association permit it Cost, heritage, façade, courtyard, fire and acoustic constraints
Low-emission electric kitchen For a menu without intensive frying or griddling Electric equipment can still produce smoke and vapour
Advanced filtration For a genuinely limited operation accepted by the designer and authority It is not a universal replacement for a roof-level discharge
External production kitchen Where food is mainly assembled or regenerated on site Reduced menu flexibility and greater logistical dependence

Important: inspect the entire extract route, including the roof, before purchasing. The existence of a duct inside the premises does not prove that it is legal, continuous, adequately sized or authorised.

4.6 Acoustic requirements

The required sound insulation depends on the administrative activity category, expected sound level, operating hours, music, equipment, adjoining rooms and acoustic zoning. There is no single decibel target applicable to every bar.

Building element Indicative solution Space allowance
Ceiling Independent suspended ceiling, anti-vibration hangers, mineral wool and multiple boards 15–30 cm
Party walls Independent lining, mineral wool and multiple plasterboard layers 10–18 cm
Floor Floating screed or dry floor over a resilient layer 5–10 cm
Façade Airtight glazing and an acoustic lobby where required Depends on the openings
Equipment Anti-vibration bases, flexible connections and silencers According to design

Important: an acoustic enclosure can reduce usable floor area, ceiling height and permitted capacity. It must be included in the concept design rather than added after the commercial layout is fixed.

4.7 Food hygiene

  • Implement a food safety system based on HACCP principles.
  • Control approved suppliers, traceability and temperatures.
  • Prepare cleaning, disinfection and pest-control plans.
  • Maintain allergen information.
  • Separate clean and dirty workflows.
  • Store chemicals away from food and food-contact equipment.
  • Use durable, washable and suitable finishes.
  • Maintain staff training records.

4.8 Waste management

  • Separate the required waste fractions.
  • Contract an authorised collector for used cooking oil.
  • Retain collection receipts and transfer documentation.
  • Provide a washable and appropriately ventilated waste area.
  • Avoid crossing waste routes with clean food preparation routes.

4.9 Pavement cafés and outdoor terraces

Madrid’s Ordinance 7/2025 on hospitality terraces and kiosks has applied since 1 January 2026. An outdoor terrace requires its own authorisation and is not automatically included in the permission to operate the indoor premises.

  • Check the required clear accessible pedestrian route.
  • Respect building entrances, crossings, trees, street furniture and utilities.
  • Submit accurate drawings and details of the proposed furniture.
  • Comply with the authorised area, operating hours and environmental conditions.
  • Budget for the applicable annual occupation fees.

Investor recommendation: do not include terrace revenue in the base financial model until the proposal has received a sufficiently reliable feasibility assessment.

4.10 Alcohol, smoking and opening hours

  • Display the required alcohol sales notices.
  • Apply Spanish smoking restrictions.
  • Display the authorised capacity.
  • Keep official complaint forms available.
  • Confirm the opening hours applying to the exact administrative category.
  • Check any additional restrictions imposed by acoustic protection zones.

5. Step-by-step permissions and project programme

  1. Define the exact activity, menu, kitchen, music, operating hours, occupancy and terrace requirements.
  2. Commission technical and document due diligence before purchasing.
  3. Survey the premises and carry out agreed opening-up inspections.
  4. Prepare a concept design and preliminary financial appraisal.
  5. Confirm homeowners’ association and shared-building requirements.
  6. Prepare the technical project, drawings, specifications, quantities and acoustic documentation.
  7. Obtain comparable construction quotations.
  8. Submit the responsible declaration or licence application and pay the applicable fees and ICIO.
  9. Deliver the work under technical supervision and a formal change-control process.
  10. Register and certify the electrical, RITE, gas and fire protection installations.
  11. Complete testing, commissioning and acoustic measurements.
  12. Submit completion and operational documentation where required.
  13. Process any outdoor terrace application separately.
  14. Complete the final inspection and pre-opening checklist.

5.1 Text-based Gantt programme

WEEK                    1-2  3-4  5-8  9-12  13-16  17-20  21-24  25-32
Due diligence           ████
Business concept        ████
Concept design               ████
Community approvals          ████████
Technical project             ████████
Declaration/licence                 ████████████████
Tendering                ████████████
Construction work                        ████████████████████
Installation registration                                        ████████
Acoustic testing                                                    ████
Pre-opening                                                           ████████
Terrace application       ████████████████████████████████
Scenario Total programme Main assumption
Best case 14–18 weeks Complete responsible declaration, existing legal duct and limited corrective work
Base case 20–32 weeks Normal design, 10–16 weeks of construction and standard registrations
Downside case 36–52 weeks or more Licence procedure, community negotiations, heritage issues, new flue or acoustic corrections

6. Indicative renovation budget

6.1 Typical cost ranges

Work package Indicative cost excluding VAT
Strip-out and waste management €60–€140/m²
Masonry, partitions and ceilings €180–€380/m²
Electrical installation and lighting €130–€260/m²
Plumbing, drainage and hot water €100–€220/m²
Air conditioning and ventilation €140–€300/m²
Gas, where applicable €25–€80/m²
Basic acoustic upgrading €180–€450/m² of premises
Minimum fire protection measures €15–€45/m²
Flooring, wall finishes and decoration €140–€300/m²
Joinery, glazing and metalwork €8,000–€25,000
Bar counter and back bar €12,000–€35,000
Kitchen equipment and extraction €25,000–€70,000
Cold storage and refrigeration €8,000–€25,000
Toilets €12,000–€28,000
Signage €2,500–€10,000
Essential furniture, fixtures and equipment €15,000–€45,000
Professional fees and studies 8–14% of construction and technical equipment
Administration, licences and fees €3,000–€10,000
Contingency 10–15%

The rates should not be added mechanically. Some apply to the entire floor area, while others relate to partial surfaces, equipment, individual units or specific service routes.

6.2 Detailed example for a 100 m² bar

Work package Cost excluding VAT
Strip-out and waste management €8,500
Masonry, partitions and ceilings €18,000
Electrical installation and lighting €17,500
Plumbing, drainage and hot water €13,000
Air conditioning, ventilation and replacement air €19,000
Basic acoustic upgrading €24,000
Fire protection, emergency lighting and signage €3,500
Flooring, tiling and decoration €18,000
Joinery, metalwork and frontage €11,000
Bar counter and back bar €18,000
Kitchen, extraction and refrigeration €35,000
Toilets, including accessible provision €16,000
Signage €4,000
Essential furniture, fixtures and equipment €20,000
Construction and equipment subtotal €205,500
Professional fees, studies and management €18,500
Administrative fee allowance €4,000
12% contingency €24,660
Total estimated investment excluding VAT €252,660
Estimated 21% VAT on taxable items €52,218
Approximate total cash requirement €304,878

This example falls above the central basic range because it includes a functional kitchen, extraction, acoustic work, furniture and complete allowances. Public fees are not subject to VAT, and the final VAT treatment should be confirmed with the investor’s Spanish adviser.

6.3 Opening costs and working capital

Cost 60 m² 100 m² 150 m²
Deposits, guarantees and utility connections €8,000–€20,000 €12,000–€30,000 €18,000–€45,000
Insurance and initial health and safety costs €1,500–€4,000 €2,000–€5,000 €3,000–€7,000
EPOS, software and telecommunications €1,500–€4,000 €2,000–€5,000 €3,000–€7,000
Opening marketing €2,000–€8,000 €4,000–€12,000 €6,000–€18,000
Opening stock €4,000–€10,000 €6,000–€15,000 €10,000–€22,000
Three-month cash reserve €30,000–€60,000 €45,000–€90,000 €70,000–€140,000

7. Basic technical and design solutions

7.1 Indicative kitchen equipment

Equipment Indicative power Design consideration
Electric griddle 6–12 kW Significant grease and smoke load
Twin fryer 12–18 kW Extraction and fire-suppression implications
Compact combi oven 7–15 kW Water, drainage and manufacturer requirements
Pass-through dishwasher 7–12 kW Steam control and dirty zone
Undercounter refrigeration 0.3–1.5 kW per unit Heat rejection into the room
Ice machine 0.5–1.2 kW Water, drainage and cleaning access
Microwave or auxiliary induction 2–7 kW Include in the electrical diversity calculation

A tapas-bar kitchen may have approximately 40–80 kW of connected electrical load before diversity is applied. The final calculation must use the selected equipment schedule.

As an early feasibility allowance, a medium commercial canopy might require approximately 2,500–6,000 m³/h of extract air. The final volume must be calculated from the canopy, cooking equipment, heat load, manufacturer’s data and replacement-air strategy.

7.2 Clean and dirty workflows

  • Delivery and goods reception.
  • Dry or refrigerated storage.
  • Clean preparation.
  • Cooking.
  • Plating and service pass.
  • Dirty-dish return.
  • Scraping and washing.
  • Drying and clean storage.

Waste and dirty crockery should not cross the route used for ready-to-serve food.

7.3 Bar counter planning

  • Provide a continuous working aisle without avoidable crossing points.
  • Separate electrical circuits for coffee machines, glasswashers, refrigeration, ice and EPOS.
  • Provide water, drainage, filtration and maintenance access.
  • Position bottle coolers, ice, glasswashing and waste according to the service sequence.
  • Consider the heat output and ventilation needs of undercounter equipment.

7.4 Energy efficiency

Measure Additional investment Indicative saving Simple payback
LED lighting and zoning controls €1,000–€4,000 30–60% of lighting consumption 1–3 years
Efficient refrigeration €2,000–€8,000 10–30% of refrigeration consumption 3–6 years
Heat recovery where viable €5,000–€15,000 10–25% of HVAC consumption 4–8 years
Operating schedules and set-point control €300–€2,000 5–15% of HVAC consumption Less than 1–3 years

These are professional estimates rather than guaranteed savings. They should be recalculated using the actual operating hours, energy tariffs, equipment, weather conditions and maintenance strategy.

8. Procurement and construction

8.1 Turnkey contract or separate trade packages?

Method Advantages Risks Best suited to
Turnkey or main contractor One main point of responsibility and coordinated programme Requires a clearly defined design and scope Investor without an experienced internal construction team
Separate trade packages Direct control of each appointment Interface disputes, delay and heavier management burden Investor supported by an experienced project manager

Recommendation: for a 60–150 m² bar, a coordinated main contract based on a completed design, measurable scope and identified specialist packages will normally reduce interface risk.

8.2 Request for proposal template

REQUEST FOR PROPOSAL — BAR RENOVATION AT [ADDRESS]

1. Contract documents: project, drawings, quantities and finishes.
2. Included and excluded work by package.
3. Responsibility for each certificate and registration.
4. Price excluding VAT, VAT amount, total and quotation validity.
5. Construction programme and long-lead items.
6. Site team, subcontractors, insurance, REA and health and safety.
7. Payment milestones and a 5% retention proposal.
8. Written change-control procedure.
9. Agreed treatment of contractor-caused delay.
10. Testing, commissioning, manuals and as-built drawings.
11. Statutory and commercial warranties.
12. Defect reporting and aftercare procedure.

8.3 Tender comparison

Criterion Weight
Comparable price and exclusions 30%
Method and programme 20%
Financial standing, insurance and compliance 15%
Verifiable hospitality experience 15%
Site team and subcontractors 10%
Warranties and aftercare 10%

8.4 Weekly site meeting template

WEEKLY SITE REPORT No. [ ]
Date: [ ]
Actual progress: [ ]%
Planned progress: [ ]%

Attendees:
[ ]

Work completed:
[ ]

Work planned for the next two weeks:
[ ]

Decisions required:
[item / responsible person / deadline]

Technical queries and incidents:
[ ]

Approved changes:
[cost / programme effect]

Quality inspections and tests:
[ ]

Health and safety:
[ ]

Items to be covered and photographic records:
[ ]

Updated risks:
[ ]

9. Risk matrix

Risk Probability Impact Response
Intended activity is not permitted Medium Critical Planning assessment before paying a non-refundable deposit
Community prevents the extract route Medium Critical Review rules and minutes and obtain written approval
Kitchen extraction is unviable Medium-high Critical Inspect the complete route to roof level
Acoustic performance is insufficient Medium High Early acoustic study, space allowance and completion testing
Hidden construction costs High High Opening-up inspections, measured design and 10–15% contingency
Insufficient electrical supply Medium High Distributor enquiry and load calculation before equipment purchase
Equipment delivery delays Medium High Early procurement and pre-approved alternatives
Terrace is refused Medium Medium-high Exclude terrace revenue from the base model
Neighbour complaints Medium High Acoustic design, door management and operating protocol

9.1 Warning signs

  • The seller states that the premises are licensed but will not provide the approved file.
  • The extract system terminates in a façade, courtyard or ceiling void.
  • The duct cannot be inspected up to roof level.
  • The physical area does not match the Land Registry or Cadastre.
  • There are adjoining homes and the business model relies on amplified music.
  • There is no credible space for accessible toilet provision.
  • The homeowners’ association has a history of disputes with hospitality operators.
  • Electrical or HVAC documentation is unavailable.
  • The construction quotation excludes testing and registrations.
  • The projected return relies on an outdoor terrace that has not been authorised.

10. Pre-opening and the first 90 days

10.1 Final inspection checklist

  • ☐ Completion certificate and applicable municipal documentation.
  • ☐ Electrical installation certificate and registration.
  • ☐ RITE certificates and registration.
  • ☐ Gas certificate where applicable.
  • ☐ Fire protection certificates and maintenance agreement.
  • ☐ Satisfactory acoustic test and sound limiter where required.
  • ☐ Extraction and replacement-air testing.
  • ☐ Air-conditioning, drainage and hot-water commissioning.
  • ☐ Emergency lighting, extinguisher, signage and escape checks.
  • ☐ Manuals, warranties, serial numbers and as-built drawings.
  • ☐ HACCP-based food safety procedures and allergen information.
  • ☐ Pest-control, cleaning and used-oil collection arrangements.
  • ☐ Insurance, official complaint forms, capacity and statutory notices.
  • ☐ Staff training in opening, closing, emergencies and food temperatures.
  • ☐ Trial service under realistic customer load.
  • ☐ Utilities, EPOS, bookings, data protection and backups.
  • ☐ Separate outdoor terrace authorisation where applicable.

10.2 Key performance indicators

Monthly sales =
customers per day × average spend × operating days

Contribution margin =
sales × (1 − variable cost percentage)

Break-even sales =
fixed operating costs ÷ contribution margin percentage

Simplified ROCE =
operating profit ÷ capital employed

Three-year ROI =
(cumulative three-year cash flows − initial investment)
÷ initial investment

10.3 Illustrative 100 m² operating scenarios

Scenario Customers/day Average spend Days/month Monthly sales Contribution margin Fixed costs Indicative monthly EBITDA
Downside 70 €16.00 26 €29,120 65% €25,000 -€6,072
Base 120 €19.00 26 €59,280 68% €29,000 €11,310
Upside 170 €22.00 27 €100,980 70% €36,000 €34,686

These scenarios are illustrations rather than forecasts or performance guarantees. They must be replaced with actual rent or financing costs, payroll, opening hours, delivery commissions, wastage, seasonality and tax assumptions.

10.4 First 90-day plan

  • Days 0–15: operate a controlled opening, measuring service times, waste, incidents and customer feedback.
  • Days 16–30: adjust staffing, purchasing, recipes, pricing and bar workflows.
  • Days 31–60: optimise product mix, gross margin, energy use and maintenance.
  • Days 61–90: update the financial model and approve further investment only when supported by operational data.

11. Editable control templates

11.1 Regulatory matrix

AREA | REQUIREMENT | APPLIES | EVIDENCE | RESPONSIBLE | DATE | STATUS | RISK

Planning | Activity compatibility | | | | | |
Community | Extract duct and equipment | | | | | |
Activity | Category and opening hours | | | | | |
Fire safety | Escape and equipment | | | | | |
Accessibility | Route and accessible WC | | | | | |
Acoustics | Study and final testing | | | | | |
Industry | Electrical, RITE and gas | | | | | |
Food safety | HACCP and allergens | | | | | |
Terrace | Separate authorisation | | | | | |

11.2 Risk register

ID | RISK | CAUSE | PROBABILITY 1–5 | IMPACT 1–5 |
EXPOSURE | RESPONSE | OWNER | DEADLINE | STATUS

12. Final recommendation for investors

The investment should be divided into two separate decisions:

  1. Purchase only when the premises have been shown to be legally and technically suitable for the intended concept.
  2. Approve the renovation only when the technical design, measured scope, contractor quotations and financial model use the same assumptions.

A fixed-price construction proposal should not be accepted before the condition of the premises, equipment schedule, acoustic design, kitchen extract route and community requirements are sufficiently defined.

Maceta y Cortafrío coordinates the construction work and different trades required for commercial premises renovations in Madrid. The construction scope should be developed in coordination with the architect or engineer responsible for the technical project and licences.

International investors assessing a commercial property can also review our property renovation service for investors in Madrid.

If you are considering purchasing premises for a new hospitality business, contact Maceta y Cortafrío to arrange an initial project assessment. Any final construction proposal will depend on the property, intended activity, existing installations, floor area and technical requirements.

Professional notice: feasibility and compliance must be confirmed by a competent architect or engineer and, where applicable, by registered professionals, authorised installation contractors, an ECU and the relevant authorities. Municipal rules, heritage status, acoustic protection zones and homeowners’ association requirements may restrict or prevent particular solutions.

13. Official sources and regulations

Regulatory verification: check the current consolidated legislation, municipal tax ordinances, planning rules, acoustic protection zones and district criteria again before submitting the application. This guide was reviewed with a reference date of 28 August 2026.

Need this service? See our Full Renovations in Madrid page.